Project Location: Glasgow, Scotland
Client: Bear Scotland
Main Contractor: John Paul Construction
Value: £1,200,000
Project Status: Complete
Start Date: May 2012
Completion Date: January 2013


Full earthworks on this brownfield heavily contaminated site of 23,000 sq.m.
Earthworks cut/fill in heavily contaminated soils and soft ground improvement techniques were utilised in minimising off-site disposal and import of fill.
Rossmore also installed the surface water, including SUDS attenuation pond, and foul drainage systems and utility ducting.
A 450mm diameter outfall pipeline was constructed across the live M74 motorway, junction 1.